|PMP Certification With a project nearly complete, the project manager has already
performed procurement closure, shared the final project report, updated the
lessons learned repository, and obtained feedback from the relevant
stakeholders. What should the project
manager do next?
A. Provide final payment to the
suppliers
B. Send a summary of how the final
product achieved the business needs
C. Transfer the completed assembly line
to operations
D. Send formal written notice to the
vendors that the contracts have been completed
HINT: All but one of the answer choices
represents an activity that has not already been completed in the scenario.
All our questions are updated to the
latest A Guide to the Project Management Body of Knowledge, standard. Stop by
at The Free PM Exam
Simulator and
try the PM Exam Simulator . We are a
Project Management Course Registered
Training Provider.
Answer and Explanation
The correct answer is C
The question implies that the Close
Project or Phase process is underway. Actions and activities necessary to
transfer the project's products, services, or results to the next phase or to
production and/or operations is one aspect of project closure. Correctly
answering this question is an exercise in the process of elimination. The
incorrect answer choices represent activities that have already been completed
by the project manager in this scenario. Of the available choices, only
transferring the completed assembly line to operations represents a closing
activity that has yet to be completed, making it the best response to the
question asked.
Details for each option:
A. Provide final payment to the
suppliers
Incorrect. The question states that
procurement closure has already been completed. Procurements are not considered
closed until final payments have been made. Therefore, the final payments must
have already been sent to the suppliers in this scenario.
B. Send a summary of how the final
product achieved the business needs
Incorrect. A summary of how the final
product achieved the business needs identified in the business plan to relevant
stakeholders is a component of the final project report. The question states
that the final project report has already been shared, making this action
redundant and unnecessary.
C. Transfer the completed assembly line
to operations
Correct. Transferring the completed
assembly line to operations is an activity that is completed during the Close
Project or Phase process. This answer choice represents an activity that
remains to be completed in this scenario.
D. Send formal written notice to the
vendors that the contracts have been completed
Incorrect. The buyer provides the seller
with formal written notice that the contract has been completed as part of the
procurement closure. The question indicates that the procurements for this
project have already been closed. Therefore, this answer choice represents an
activity that has already been completed in this scenario. Click Here